In-Progress: 47th Street

Now that we’ve finished the first phase of interior removals, the excavation phase begins. This includes the underpinning of the neighboring buildings and front wall, as well as 6’ of bedrock excavation. These photos showcase preparation for the pouring of concrete foundation walls by way of sheeting, shoring, line drilling and lagging. The steel bracing holds up the existing four floors while excavation is finished.